IFC 4.3.2.20240128 (IFC4X3_ADD2) under development

6.5.4.4 Pset_ProjectOrderChangeOrder

6.5.4.4.1 Semantic definition

A change order is an instruction to make a change to a product or work being undertake. Note that the change order status is defined in the same way as a work order status since a change order implies a work requirement.

6.5.4.4.2 Applicable entities

6.5.4.4.3 Properties

Name Property Type Data Type Description
ReasonForChange IfcPropertySingleValue IfcText

A description of the problem for why a change is needed.

BudgetSource IfcPropertySingleValue IfcText

The budget source requested.

Table 6.5.4.4.A

Edit on Github


Is this page difficult to understand? Let us know!

6.5.4.4.4 Changelog

6.5.4.4.4.1 IFC4