7.3.5.3 Qto_LaborResourceBaseQuantities

7.3.5.3.1 Semantic definition

Base quantities that are common to the definition of all occurrences of labour resources.

7.3.5.3.2 Applicable entities

7.3.5.3.3 Properties

Name Data Type Description
StandardWork IfcQuantityTime

Work that is performed at regular times, up to a particular limit after which overtime rates may apply.

OvertimeWork IfcQuantityTime

Work that is performed after exceeding a particular limit such as hours per day and/or hours per week, after which company or municipal policy requires a different rate to apply. Note: Policies for when overtime takes effect are the responsibility of the user or application; they are not modelled in IFC.

Table 7.3.5.3.A

Edit on Github


Is this page difficult to understand? Let us know!

7.3.5.3.4 Changelog

7.3.5.3.4.1 IFC4

  • New resource